D
Donal P
For some reason, Project has decided to count one task multiple times in each
of the resources assigned to it. I assigned up to five people to several
tasks in the Gantt chart view, and then when I went to level the resources in
the 'resource usage' view I noticed that some (but not all) of the tasks were
counted multiple times. This leads to serious overbooking of the resources.
Any thoughts on why this is happening, and what I can do to fix it?
I also noticed that the dependencies in some of the duplicated tasks got
replicated by the same number of times the tasks repeated for the resource.
That is, the dependency of one task (which was duplicated four times in a
particular resource) was shown as '12,12,12,12' - instead of the '12' I had
initially put there.
Thoughts, anyone? TIA...
of the resources assigned to it. I assigned up to five people to several
tasks in the Gantt chart view, and then when I went to level the resources in
the 'resource usage' view I noticed that some (but not all) of the tasks were
counted multiple times. This leads to serious overbooking of the resources.
Any thoughts on why this is happening, and what I can do to fix it?
I also noticed that the dependencies in some of the duplicated tasks got
replicated by the same number of times the tasks repeated for the resource.
That is, the dependency of one task (which was duplicated four times in a
particular resource) was shown as '12,12,12,12' - instead of the '12' I had
initially put there.
Thoughts, anyone? TIA...