Chris Jewell
I am developing a Programme Plan with 50+ projects each providing resource
and schedule information. I am trying to use project to display this
information in Ghant Chart and Resource Tables. Unfortunately as we replan
the schedule, the resource allocations automatically update to the new dates
(good!) but change the values (bad!) as we rely on the PMs providing the new
information regarding resources. Is it possible to shift the resource
allocations month by month without adjusting the values? Probably a stupid
question, but any assistance appreciated.
Windows XP
Office 2002
MS Project 2003 Standard
and schedule information. I am trying to use project to display this
information in Ghant Chart and Resource Tables. Unfortunately as we replan
the schedule, the resource allocations automatically update to the new dates
(good!) but change the values (bad!) as we rely on the PMs providing the new
information regarding resources. Is it possible to shift the resource
allocations month by month without adjusting the values? Probably a stupid
question, but any assistance appreciated.
Windows XP
Office 2002
MS Project 2003 Standard