toast88
What is the best way to see revised target dates for tasks in MSP.
Example: Task 1 had a target date of 8/26 (fixed units, effort driven), but
the resource assigned was out sick for a week. The planned finish date in MSP
does not change from 8/26 even though no time was booked to it, but reality
is the task was not done on time. What is the best way to see the new
practical date - recalculate the new finish date and all successor tasks
throughout the plan?
Thanks!