I have a group of support I want to lock out for a resource during the remaining year
J John M Jul 23, 2007 #1 I have a group of support I want to lock out for a resource during the remaining year
J Jim Aksel Jul 23, 2007 #2 Insert/Recurring Task.... Specify the parameters as needed. Assign resources in a second step -- If this post was helpful, please consider rating it. Jim It''s software; it''s not allowed to win. Visit http://project.mvps.org/ for FAQs and more information about Microsoft Project