M
Mark
Hello All.
I am running Project 98 but will be upgrading soon. In 98, I have a master
schedule that has 2 project schedules. I have the same resource in both
project schedules and the resource is working on both at the same time. 98
does not show a conflict for the resource. Will the new versions show
resource allocations across projects? If not, is there a way to solve this?
Thanks in advance.
Mark
I am running Project 98 but will be upgrading soon. In 98, I have a master
schedule that has 2 project schedules. I have the same resource in both
project schedules and the resource is working on both at the same time. 98
does not show a conflict for the resource. Will the new versions show
resource allocations across projects? If not, is there a way to solve this?
Thanks in advance.
Mark