same work hrs, same %, same end date

I'm trying to both A and B members on 2 different tasks by putting the same
work of 100 hours with 75% of resource. I'm expecting same end date, but I
get some thing different. Could you guide me how to get this, and things that
are required to take care
 
M

Mike Glen

Hi ???,

Welcome to this Microsoft Project newsgroup :)

Have the resources have the same calendar and same start date/time? What is
the Duration of each? Which version of Project are you using?

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #5 and 10, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the articles before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
J

Jack Dahlgren

What is the different thing that you are getting?
Is the start date exactly the same? Do both A and B have the same calendar?

-Jack Dahlgren

"same work hrs, same %, same end date" <same work hrs, same %, same end
(e-mail address removed)> wrote in message
news:[email protected]...
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top