J
James McCloskey
I have a small project (~100 tasks) which I am trying to schedule based on a
few main constraints: a completion deadline (1/01/2008), periodic go/no-go
checkpoints (at pre-existing monthly review meetings), and some resource
limitations.
For some reason, the levelled (by week) project has a 3-week "dead space" in
it: there are NO tasks assigned to any resources for this 3-week period. But
there are subsequent resource over-allocations, on tasks that ought to be
able to be done during that "dead space". I've pored over the tasks looking
for any odd predecessor relationships, but I've found nothing.
Any idea what might be causing this?
And advice is greatly appreciated!
few main constraints: a completion deadline (1/01/2008), periodic go/no-go
checkpoints (at pre-existing monthly review meetings), and some resource
limitations.
For some reason, the levelled (by week) project has a 3-week "dead space" in
it: there are NO tasks assigned to any resources for this 3-week period. But
there are subsequent resource over-allocations, on tasks that ought to be
able to be done during that "dead space". I've pored over the tasks looking
for any odd predecessor relationships, but I've found nothing.
Any idea what might be causing this?
And advice is greatly appreciated!