B
Barry
Is there a way to make the scheduled finish date change when the % complete
is changed? There does not appear to be a linkage.
is changed? There does not appear to be a linkage.
Barry said:Is there a way to make the scheduled finish date change when the % complete
is changed? There does not appear to be a linkage.
Barry said:Is there a way to make the scheduled finish date change when the % complete
is changed? There does not appear to be a linkage.
John said:Barry,
Ok, I'll bite, why would the scheduled finish date be expected to change
when progress changes?
The idea behind scheduling is that the duration of a task is defined by
its start and finish dates. As the task is worked, progress is recorded
(i.e. % complete). The main reason the scheduled start date may change
is because the task was actually started earlier or later than the
scheduled start. If the actual start date changes, then the finish date
would also normally change. Or, the finish date might change for example
if more resources are added to speed up the task. Percent complete
simply records progress - it doesn't change the basic parameters of the
task.
John
Project MVP
Barry said:John,
Assume a task is started and the actual date is entered. Assume further
that progress is ahead of schedule. Shouldn't the scheduled finish date
move to the left, when the % complete is entered?
Barry
Barry said:John,
Assume a task is started and the actual date is entered. Assume further
that progress is ahead of schedule. Shouldn't the scheduled finish date
move to the left, when the % complete is entered?
Barry
Barry said:Thanks for the responses. You've answered my question.
Barry
John said:Barry <[email protected]> wrote:
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.