Rudy
I have a simple scheduling problem. On a new project using the default
calendar (8:00AM - 5:00PM), I create a task and assign a resource to the task
working at 25% units with 4hrs of work. Let's say the task starts on March 2,
2005 8:00AM. The finish time is on March 3, 2005 5:00PM. Isn't the task
suppose to finish at 10:00AM?
If I change the allocation units to different values (like 14%) I get even
more weird results (finish time: 1:34PM).
Has anyone figure out how Project Pro determines the finish time of a task?
Thanks,
- Rudy
calendar (8:00AM - 5:00PM), I create a task and assign a resource to the task
working at 25% units with 4hrs of work. Let's say the task starts on March 2,
2005 8:00AM. The finish time is on March 3, 2005 5:00PM. Isn't the task
suppose to finish at 10:00AM?
If I change the allocation units to different values (like 14%) I get even
more weird results (finish time: 1:34PM).
Has anyone figure out how Project Pro determines the finish time of a task?
Thanks,
- Rudy