Scheduling Resources based on availability

L

learningaccess

I am currently trying to complete a Gantt Chart for a project i am managing.
I need to schedule specific tasks based on the availability of each
individual resource. For instance, i can not have two parts programmed at the
same time because there is only one programmer working this job. I also
cannot have two parts machined at the same time because we only have one of
that specific machine. I was told there is a way to achieve this ability, but
i am unsure as to where to start.

Thanks,
 
J

JulieS

Hi learningaccess,

If you have created the resources, you may assign the resource to both of
the programming tasks. This will cause an overallocation of the programmer
resource. You may then use Resource Leveling (Tools > Level Resources) to
have Project delay one of the tasks to a time when the resource is
available.

You may wish to have a look at Mike Glen's excellent series of articles
about Project at:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23

Hope this helps. Let us know how you get along.

Julie
 
L

learningaccess

Thank you very much. Those articles are a BIG help. Your comments also made
it more clear.
 
J

JulieS

Hi learningaccess,

You are welcome and thanks for the feedback. I agree whole heartedly --
Mike's articles are super!

Julie
 