Michael Vestel
When I’m scheduling resources, I prefer to use Fixed Duration so that I can
say how long a task is and then assign the percent effort for the various
resources. I also Click Effort driven dialog box. This works fine if I put in
all the resources correctly the first time. But if I choose to add one later
at anything OTHER than 100%, I get the following error: “Project cannot
create an assignment with a specific unit value on a fixed duration,
effort-driven task. Once the assignment is created, you can edit the unit
value on the assignmentâ€
So I have to add the new resource at 100% and come back and edit it again.
The problem is that it recalculates the other resources effort% when I add
the new resources at 100%. So I have to re-enter ALL of the resources %
effort. This work around is very frustrating.
Is there a better way?
say how long a task is and then assign the percent effort for the various
resources. I also Click Effort driven dialog box. This works fine if I put in
all the resources correctly the first time. But if I choose to add one later
at anything OTHER than 100%, I get the following error: “Project cannot
create an assignment with a specific unit value on a fixed duration,
effort-driven task. Once the assignment is created, you can edit the unit
value on the assignmentâ€
So I have to add the new resource at 100% and come back and edit it again.
The problem is that it recalculates the other resources effort% when I add
the new resources at 100%. So I have to re-enter ALL of the resources %
effort. This work around is very frustrating.
Is there a better way?