D
Doug
Hello all,
I am trying to do what seems VERY simple, however, Project makes this next
to impossible, unless I'm just missing something. All I want to do is enter
in a start date for a task and an end date for a task. Then I want to assign
people to that task. I can do all this just fine, but now I've been reading
that the percentage units really have nothing to do with how much time of
their day they spend on the project. When I go to resource graph, I want to
see how much time eveybody is allocated overall. However, this doesn't seem
to be happening. For instance, I have somebody allocated at 80% (which took
me about an hour of fiddling to get it off of the 100% that it kept reverting
to), but on the graph, it shows them at 20%. Why?
Is there not just a simple way I can enter project start, finish, and
resource percentage and show that graph?? That's ALL I want to do, and for
whatever reason, I haven't been able to.
Thanks.
I am trying to do what seems VERY simple, however, Project makes this next
to impossible, unless I'm just missing something. All I want to do is enter
in a start date for a task and an end date for a task. Then I want to assign
people to that task. I can do all this just fine, but now I've been reading
that the percentage units really have nothing to do with how much time of
their day they spend on the project. When I go to resource graph, I want to
see how much time eveybody is allocated overall. However, this doesn't seem
to be happening. For instance, I have somebody allocated at 80% (which took
me about an hour of fiddling to get it off of the 100% that it kept reverting
to), but on the graph, it shows them at 20%. Why?
Is there not just a simple way I can enter project start, finish, and
resource percentage and show that graph?? That's ALL I want to do, and for
whatever reason, I haven't been able to.
Thanks.