P
Pam
How do I get project to calculate start and end dates
correctly when I have a resource that is 50% allocated - 4
hrs each day based on a 40 hr week? I have set this
resource up in the resource sheet at 50% and I have
changed their working time to reflect 4 hrs a day M-F but
when I assign them to a 20 hour task, project calculates
that the task will be complete in 2.5 days instead of in 5
days.
The task is set up as a fixed unit/effort driven task.
I am using project 2000.
thanks!
correctly when I have a resource that is 50% allocated - 4
hrs each day based on a 40 hr week? I have set this
resource up in the resource sheet at 50% and I have
changed their working time to reflect 4 hrs a day M-F but
when I assign them to a 20 hour task, project calculates
that the task will be complete in 2.5 days instead of in 5
days.
The task is set up as a fixed unit/effort driven task.
I am using project 2000.
thanks!