J
Josh
I am trying to set up a task that tasks a small amount of time (an hour for
example) but the start and finish dates are about a week apart, causing the
duration time to be much larger than it actually is. In other words, the
task needs to be done during this week, but it does no take a week to do. Is
there any way to set it up so that it doesn't effect the duration time and
still shows the accurate start and finish dates?
example) but the start and finish dates are about a week apart, causing the
duration time to be much larger than it actually is. In other words, the
task needs to be done during this week, but it does no take a week to do. Is
there any way to set it up so that it doesn't effect the duration time and
still shows the accurate start and finish dates?