D
Dave
For the projects information, we have both a set start date and a set finish
date. We can not allow the program to then change the overall project
timeline based on the tasks entered. We need to control both, the overall
start/end and each task's start/end.
We have been trying to use constraints in task info but it still shifts that
other task start & end dates if we make any changes. It's that the tasks
link to each other and make shifts with the slightest change. Also I think we
have set start and end date for overall projects in project info dialog box.
What is the best way to control both the start and end of the project and
each task so that they do not change and these are inflexible constraints. We
cannot seem to do it correctly. Please let me know what we may be doing wrong
or what functions could help.
Many Thanks
David
date. We can not allow the program to then change the overall project
timeline based on the tasks entered. We need to control both, the overall
start/end and each task's start/end.
We have been trying to use constraints in task info but it still shifts that
other task start & end dates if we make any changes. It's that the tasks
link to each other and make shifts with the slightest change. Also I think we
have set start and end date for overall projects in project info dialog box.
What is the best way to control both the start and end of the project and
each task so that they do not change and these are inflexible constraints. We
cannot seem to do it correctly. Please let me know what we may be doing wrong
or what functions could help.
Many Thanks
David