Setting up a Resource calendar

D

Dave Lugo

Hello,

I would like to create a Calendar that would show individuals availability
so I can see if certain people are available for certain projects. What do i
need to do to create a calendar that a Project Manager can read to check on
people's availabilty
 
J

Jan De Messemaeker

Hi,

Set up the resource calendar through Tools, Change Working time, and look at
the resoure usage view, inserting a line (through Detail DStyles) "Remaining
Availability"
HTH
 