dsta said:
Hi,
I am new to Project, and I'm trying to schedule some tasks which are not
actually time / resource dependant - for example, the signing and returning
of paperwork from the client. How am best to do this? I want to allocate a
period of time to this (ie one month) during which it can take place, but
also to somehow place no days work against it. Howeve when I do this I am
unable to set completion percentages. (As only one of two cotnracts may have
been signed.)
Thanks!
dsta,
If you have assigned a resource to the paperwork tasks, then by
definition there will be work hours involved. However, if the paperwork
task is intended strictly as a non-resource accounting of paperwork
activity, you could do the following.
First, enter the task as fixed duration (select the task and go to
Project/Task Description/Advanced tab and set the task type as "fixed
duration"). Second, you might want to consider entering calendar time
(in lieu of the default working time), in the duration field of the
task. Do that by using "ed" after the value. For example, 30ed for 30
elapsed days. Third, do not assign any resources to the task.
Then if you have 4 separate paperwork actions represented by the task
and 2 of them are signed and returned, enter 50% in the % Complete
field. Keep in mind though that if one or more of the actions is not
completed by the finish date, you will need to extend the duration AND
then re-enter % complete since the % Complete field is based on the
Duration field.
Other options you might want to consider. Use a separate task line for
each paperwork action. That will give you greater control. You might
just want to do each one as a completion milestone. In other words, its
completion is required by a certain date and it's either done (100%) or
not done (0%). Or, you could use a couple spare number fields to keep
track of total paperwork actions and how many have been done and leave
the task itself as simply a placeholder of time in your schedule.
Hope this helps.
John
Project MVP