Sharing resource

K

Kelson

Hello

I`ve got 5 tasks running at the same time by the same number of resource.
How can I share this resource for all 5 tasks?

e.g. 5 tasks for 1 person = like 0,2 person per task

I wanna set the real person (1) for each task and then the MSProject make
the rest. Does anybody help me?

Thanks in advance
 
J

JulieS

Hi Kelson,

Project will not assign resources for you. You have a couple of
options. Select all 5 tasks. Click the Assign Resources button on the
Standard toolbar and in the units field enter 20% (if you have
assignment units set to %) or .20 (if you have assignment units set to
decimal.)

The other option is to assign the resource at 100% or 1 and then use the
resource leveling command to have Project spread the assignments.
However, this will most likely set the tasks to happen in sequence (A
then B then C etc.) rather than all at one time.

I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
J

Jan De Messemaeker

Hi all,

It has to be said that this is a far better solution for the project since
now there will be a few tasks finished real early whereas in the 0,2 option
all tasks will finish simultaneously, all just as late.
Greetings,
 