Jan said:
Hi,
What exactly do you mean by link into the project properly?
When you use the word "properly" I suspect they have some sort of dependency
anyhow.
If they have no dependency at all, then the earliest start is the project
start and the late fiinish is the project finish.
What are the criteria to say it will start "earlier than necessary"?
Isn't "necessary" the expression of some dependency?
In other words, to me a project plan should reflect reality as much as
possible..
Hope this helps
If a task can't start prior to a specific date, it is almost always
because of one of 2 things. The first is an external constraint, like a
delivery to a customer who requires it by that date, or a government
regulation that requires it. The other reason is that it depends on
some other task or tasks. Almost all tasks have one or the other of
these conditions. Exceptions are very rare.
If you think logically about it, if a task has no predecessor and no
successor, and no time constraint on it, it can start the day the
project starts, and can finish the day the project finishes. So it can
be done anytime during the project duration. How many tasks like that
do you have on your projects?
I teach my students to make sure their projects have "Schedule
Continuity". That is, every task, with very few exceptions, has at
least one predecessor and one successor. The only common exception I
can think of, after over 25 yrs of CPM scheduling, are regularly
scheduled meetings. Like a weekly Project Status meeting. It's not
really dependent on anything else happening, it just occurs every week.
So doesn't have to be linked.
To achieve Schedule Continuity, I was taught by a scheduling expert
many years ago to create 2 special milestones, "Start" and "Finish".
Any task that does not otherwise have a predecessor is a successor to
"Start" and any task that does not otherwise have successor is a
predecessor to "Finish". If you look at scheduling software developed
by professional schedulers (Project was not), these 2 milestones are
built in to every schedule, and can't be deleted. You're forced to
create your schedule linked between these 2 milestones. This is the way
the "experts" who developed the software are trying to show that
everything is linked. In this system, even the meetings would be
following the Start milestone and preceding the Finish milestone and
linked accordingly.
There are those who disagree with this methodology. In my experience,
it resolves many of the problems people have in getting Project to
function properly, especially with features like tracking, resource
leveling and others. Some consider it a "best practice", I consider it
a neccessity for a fully fuctional Critical Path Method schedule.
I hope this helps in your world.