M
Mike R.
Is there a way to have a column that displays the number of days from Project
start to the start of a task?
I would like to show that WBS 3.2.1, on Line 500, starts X days after the
project starts. Then show 3.2.2, on line 501, starts y days after the project
start.
Can this be done??
Thanks,
Mike R.
start to the start of a task?
I would like to show that WBS 3.2.1, on Line 500, starts X days after the
project starts. Then show 3.2.2, on line 501, starts y days after the project
start.
Can this be done??
Thanks,
Mike R.