B
Bill Fitz-Holland
We are trying to update progress in MS Project. What we want to do is have
both the task bar and the baseline for the task visible. We have done this
successfully, and our baseline is a hollow block. We want to be able to fill
in the baseline according to the percentage completion of the task,
regardless of any changes we may make to the actual task duration, start, or
finish dates. This requires another bar style and originally this was done,
with the bar starting at the baseline start and ending at the physical
percentage completion. This only works correctly if the baseline and the
task bar have the same start and end dates. As soon as dates, or durations
are altered, it no longer does what we want it to. If we have 25% of the
work complete for a task, we want 25% of the baseline to be filled in,
regardless of whether the durations, or dates are of baseline and current
plan are the same.
The only way we seem to be able to this, is by customising fields to
calculate the percentage complete as a duration of the baseline and then
adding it to the baseline start date.
both the task bar and the baseline for the task visible. We have done this
successfully, and our baseline is a hollow block. We want to be able to fill
in the baseline according to the percentage completion of the task,
regardless of any changes we may make to the actual task duration, start, or
finish dates. This requires another bar style and originally this was done,
with the bar starting at the baseline start and ending at the physical
percentage completion. This only works correctly if the baseline and the
task bar have the same start and end dates. As soon as dates, or durations
are altered, it no longer does what we want it to. If we have 25% of the
work complete for a task, we want 25% of the baseline to be filled in,
regardless of whether the durations, or dates are of baseline and current
plan are the same.
The only way we seem to be able to this, is by customising fields to
calculate the percentage complete as a duration of the baseline and then
adding it to the baseline start date.