J
Jenn
Hi! I am new to ms project. Here is my question. I have a task that has a start date and a finish date. There always has to be a target finish date for this example. If I miss the finish date I created, I want to show 1) the task is still ongoing since the intial start date 2) the missed "finish date" (as a milestone or something like that) 3) the new "Finish date" that I have created. I want the duration to be from the start to the new finish date and not from the start to the original finish date that I did not meet. (Basically I want to show my customer here are all the dates you keep setting as your "finish date" but you keep blowing by them and here is how long it has taken so far.)
Any suggestions? Thanks in advance!
Jenn
Any suggestions? Thanks in advance!
Jenn