M
matthewg156
I have a very simple scenarion:
Summary Task (duration 1 day)
- Task 1 (duration 1 day)
- Task 2 (duration 1 day)
- Task 3 (duration 1 day)
If I assign resource Bob to each of these tasks, the summary task reflects a
duration of 1 day. But Bob can't do all of these tasks at the same time! I.e.
the problem here seems to be that project doesn't take into account
scheduling on a resource basis.
I don't want to have to assign dependencies, because in reality there aren't
any, i.e., task 2 does not depend on task 1, etc - they can be done in any
order.
Is there any way to get project to add the summary task duration taking into
account resource allocation?
Summary Task (duration 1 day)
- Task 1 (duration 1 day)
- Task 2 (duration 1 day)
- Task 3 (duration 1 day)
If I assign resource Bob to each of these tasks, the summary task reflects a
duration of 1 day. But Bob can't do all of these tasks at the same time! I.e.
the problem here seems to be that project doesn't take into account
scheduling on a resource basis.
I don't want to have to assign dependencies, because in reality there aren't
any, i.e., task 2 does not depend on task 1, etc - they can be done in any
order.
Is there any way to get project to add the summary task duration taking into
account resource allocation?