Snapshot of Remaining Work in the Past

J

jamos

Hello -- I would like to create a burn-down chart including snapshots of
Remaining Work and Work over the days from the past couple of months. Is
this information stored anywhere from which I can export it?

Thanks!
 
J

Jack Dahlgren

Not unless you stored it in a baseline or another copy of the schedule.
Sorry.

-Jack Dahlgren
 
R

Redneck David

Do you save a new version of the file each time you save it?

Project does calculate the information needed to create a burndown chart but
you would be well-advised to go ahead and baseline now.
 