I am using Project 2003 and am trying to adjust the way task progress is
shown in using the options described in Help and Online at
http://office.microsoft.com/en-gb/project/HP430082591033.aspx?pid=CH010426671033.
However, I must be doing something wrong because no matter what I do with
status date, actual start, % complete, actual and remaining duration nothing
changes !! Do you have any suggestions as to other settings that may be
preventing this functionality from working.
 
M

Mike Glen

Hi skeddr,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #26 on progressing, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question