S
Sameer
Dear All;
I have a huge project plan and in that plan there are two tasks where the
CPI is around 3.0 and the SPI is 0.......
Is this sort of a situation possible? If yes then can anyone give me a
scenario where i can try to reproduce this?
Regards
Sameer
I have a huge project plan and in that plan there are two tasks where the
CPI is around 3.0 and the SPI is 0.......
Is this sort of a situation possible? If yes then can anyone give me a
scenario where i can try to reproduce this?
Regards
Sameer