Perhaps a formula in a spare text field. You could compare duration to the
projDateDiff function. If a task is contiguous, projDateDiff and Duration
will be the same. If [Duration]>projDateDiff() then the task is split and
you could return "True" or another value to Text1.... then use a graphical
indicator if desired.
Caution: projDateDiff calculates with units of minutes so you will need to
compare [Duration] in minutes to projDateDiff. The conversion will depend on
hours/day, etc. There are 480 minutes in an 8 hour day.
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.