kamiar said:
Hi John,
Thanks a lot for your explanation.
You are right about the measuring performance in overall (the important
things is start and finish), but something is miss and it is the trend of
progress for long task(as you mention by S_Curve). Furthermore when you save
project as baseline and you set Gantt chart layout you can see the split
portions of a task in the graphic part of Gantt chart and if you change the
data of baseline (such as start and finish) you can follow the change such as
real task for example if you change the baseline start duration of first
portion is fixed and the portion just will move. So this is why I think that
somewhere the information must be exist, but maybe there isn’t any way to
capture this data , in this case it is lack of ms.project.
If you find any thing in this regard say me
My personal e_mail is (e-mail address removed)
Best regards
Kamiar
kamiar,
If you are referring to the split that can be seen in the baseline bar
in the Tracking Gantt view, I know of no way other than what I suggested
previously to get the split part start and finish for the baseline. Just
because something shows on Gantt graphic doesn't mean that data is
accessible either in a Project field or via VBA. In this case I do not
agree that the lack of this information is a fault of Project.
I just don't see the value in tracking baseline splits. Splits are an
interruption in the task work flow. If a task is baselined and then the
task splits, the performance measurement is against the original plan.
For the standpoint of performance to plan, who cares if the task split?
The fact is, the performance metric is likely to be negative because the
split will generally cause the Finish date to move out. The only
important question I can see is, does the reason for the split justify a
re-set of the baseline? Perhaps, but generally not. The task slipped and
the performance metric should show that.
John
Project MVP