Splitting tasks

J

JFrancisco

I am using MP2002 and have several tasks that I need to split. I am hitting
the split task icon on the standard toolbar, getting the symbol and box, but
when I drag the bar nothing happens. What am I doing wrong?
 
G

Gérard Ducouret

Hello Francisco,
After hitting the Split Task icon, Click the task bar where you want to
split it.
That's all ;-)

Gérard Ducouret
 
J

JFrancisco

Thanks. Thats what I was doing. Nothing happens. I can hit the icon and click
where I want the split, or hit the icon and click and drag on the bar, either
way, I don't get a split. Any suggestions?
 
G

Gérard Ducouret

Strange ...
Check the Calculation options:
Tools / Options / Calculation / Calculation mode : automatic

Gérard Ducouret
 
J

JFrancisco

Perfect. Thanks. What else is affected by my having the calculation in manual?
 
J

Jan De Messemaeker

Hi JF,

Simply said: everything.
With calculation set to manual Project stops calculating dates.
For instance you might set a constraint Must Start On 8/8/5 the task
woiuld'nt move either.
 