Start and Finish dates determined by links, dynamic duration

  • Thread starter Long Haired Git
  • Start date
L

Long Haired Git

I need to show a "provide on-call support" task for several support teams for
an IT project.
The start of this on-call support for my project is linked to the start
date/time of the first activity on the cut over weekend.
The end is determined by the finish date/time of the last activity on the
cut over weekend.
Thus, the actual duration is dynamic so I want it calculated.

I've added predecessors as "xFS, yFF" (where x and y are task ids), just
need to be told what option I flick (there are so many) to enable this
dynamic duration....
 