J
jdee
I have Task A that starts on 4/3/06 and finishes on 4/28/06. There are three
resources assigned to it. Only 40 hours of work will take place during this
timeframe. When I enter in 40, the finish date jumps to 4/7/06. How do I keep
this from happening?
I am using Project 2003
J
resources assigned to it. Only 40 hours of work will take place during this
timeframe. When I enter in 40, the finish date jumps to 4/7/06. How do I keep
this from happening?
I am using Project 2003
J