Henry St Aubyn
Hello,
I am trying to shedule a summary task (ST1) to start so that it finishes at
the same time that a sub-task under another summary task (ST2) begins. ST2
lasts 8 weeks and ST1 lasts 3 weeks, the sub-task under ST2 begins 6 weeks
into it. So, I want ST1 to start 3 weeks into ST2. With me so far?!?
Project won't let me assign a 'Start-to-Finish' dependency between the
sub-task and ST1 so I am forced to use a 'Start-to-Start' dependency with a 3
week time lag. Obviously this is not ideal, as any change to ST1's duration
will not change its start date - to do this requires me to manually change
the time lag to equal the duration of ST1.
If anyone can understand this and help me I would be very grateful,
Henry
I am trying to shedule a summary task (ST1) to start so that it finishes at
the same time that a sub-task under another summary task (ST2) begins. ST2
lasts 8 weeks and ST1 lasts 3 weeks, the sub-task under ST2 begins 6 weeks
into it. So, I want ST1 to start 3 weeks into ST2. With me so far?!?
Project won't let me assign a 'Start-to-Finish' dependency between the
sub-task and ST1 so I am forced to use a 'Start-to-Start' dependency with a 3
week time lag. Obviously this is not ideal, as any change to ST1's duration
will not change its start date - to do this requires me to manually change
the time lag to equal the duration of ST1.
If anyone can understand this and help me I would be very grateful,
Henry