I
Iona
Hello,
I am desperately looking for help on 2 things.
First, a formula to help me determine the number of days behind for a task.
I would like to take into consideration if there is an actual start date. I
am using Baseline2 as my comparison point. However, based on a MVP's prior
email I found in the Discussion Room dated 12/3/08 (I copied it below), their
considerations sound much more comprehensive (complete) then mine.
What is the best way to go about this? Should I be taking the percentages
and Baseline2 Finish date into consideration when advising my PM a task is
behind?
The formula I tried looks like this...
IIf ( [Actual Start] ="NA"AND [Baseline2 Start] <NOW(), [Baseline2
Start]-NOW(), "On Schedule" )
12/3/08 MVP - Jim Aksel
It is actually much more complicated than that, if a task started yesterday
and is 100 days long, it will only be 1% complete today. That task is on
schedule and should show green. The formula provided would indicate red.
Similarly, a task that is 100 days long should be 95% complete on day 95.
If the user claimed 80% they are behind schedule and should show yellow or
red, not the green indicated by the formula.
So the formula needs to be sensitive to the start date and an expected rate
of completion.
--
Secondly, for the stop lights I would like to cross reference the Days
Behind Column durations that it comes up with from the formula requested
above.
I appreciate any help.
Thank you,
Beginner
I am desperately looking for help on 2 things.
First, a formula to help me determine the number of days behind for a task.
I would like to take into consideration if there is an actual start date. I
am using Baseline2 as my comparison point. However, based on a MVP's prior
email I found in the Discussion Room dated 12/3/08 (I copied it below), their
considerations sound much more comprehensive (complete) then mine.
What is the best way to go about this? Should I be taking the percentages
and Baseline2 Finish date into consideration when advising my PM a task is
behind?
The formula I tried looks like this...
IIf ( [Actual Start] ="NA"AND [Baseline2 Start] <NOW(), [Baseline2
Start]-NOW(), "On Schedule" )
12/3/08 MVP - Jim Aksel
It is actually much more complicated than that, if a task started yesterday
and is 100 days long, it will only be 1% complete today. That task is on
schedule and should show green. The formula provided would indicate red.
Similarly, a task that is 100 days long should be 95% complete on day 95.
If the user claimed 80% they are behind schedule and should show yellow or
red, not the green indicated by the formula.
So the formula needs to be sensitive to the start date and an expected rate
of completion.
--
Secondly, for the stop lights I would like to cross reference the Days
Behind Column durations that it comes up with from the formula requested
above.
I appreciate any help.
Thank you,
Beginner