stop task splitting

L

Larry

I have turned off task splitting on both the Options menu and the resource
leveling control. Nonetheless, MS project splits my tasks when I resource
level. How do I stop this?
 
L

Larry

Hi, Jan

I can check and take them out. Do I need to take out Sunday as non-working
also?
 
J

Jan De Messemaeker

Hi,

No, what I meant is days off that are differnt from the days off in the
Project calendar (and thus may lead to non-simultaneous work for different
resources on one task)
HTH
 
L

Larry

Hi, Jan

I don't think holidays were the problem, but the overall calendar use
appeared to be causing the trouble.

I started a new file with first resetting the standard calandar, and then
pasted all the stuff from the broken file. It works fine now, without
splitting or changing the durations.

Thanks for your thoughts.

Larry
 