S
strepxe
Hi,
I am using Microsoft Project 2003 Standard Edition and getting some
unusual behaviour.
1. I create a number of tasks (a,b,c)with different durations etc. -
no problem
2. I then link the tasks with task 'b' having 'a' as a predecessor and
'c' having 'b' as a predecessor + type = "Finish To Start (FS)"
Whatever I do all three tasks start at the same time i.e. task 'b'
will not start when task 'a' finishes and so on.
I'm really going a bit crazy here - this is one of the basic things
project is supposed to do and I'm not getting it (literally!)
I'd really appreciate any guidance folks on this group could offer me!
G
I am using Microsoft Project 2003 Standard Edition and getting some
unusual behaviour.
1. I create a number of tasks (a,b,c)with different durations etc. -
no problem
2. I then link the tasks with task 'b' having 'a' as a predecessor and
'c' having 'b' as a predecessor + type = "Finish To Start (FS)"
Whatever I do all three tasks start at the same time i.e. task 'b'
will not start when task 'a' finishes and so on.
I'm really going a bit crazy here - this is one of the basic things
project is supposed to do and I'm not getting it (literally!)
I'd really appreciate any guidance folks on this group could offer me!
G