T
Tom
Hi,
I have two tasks, on task has a 'must start on' constraint of 2/1/05,
duration of 3 days so it ends on 2/4/05. The sucessor task has a constraint
of 'as soon as possible' a type of 'finish-to-start' and zero lag days. But,
MS Project calculates a start date of 4/4/05??? There is no other linkages
and both tasks are NOT turned on for 'effort driven'. Why oh why would MS
Project create this lag time? Both tasks are detailed tasks within the same
summary task.
I have two tasks, on task has a 'must start on' constraint of 2/1/05,
duration of 3 days so it ends on 2/4/05. The sucessor task has a constraint
of 'as soon as possible' a type of 'finish-to-start' and zero lag days. But,
MS Project calculates a start date of 4/4/05??? There is no other linkages
and both tasks are NOT turned on for 'effort driven'. Why oh why would MS
Project create this lag time? Both tasks are detailed tasks within the same
summary task.