Wahou
My MSP is playing tricks on me. All my summary tasks appear to start at the
PROJECT START DATE. Even when the tasks underneath the summary tasks start
later, the summary task does not adopt that start date, it stays fixed at the
project start date (which makes the daycount wrong). The end date of the
summary task adjusts, though. What is going on ? thks