E
Ebbe
I am trying again. Now WITH a subject 
Hi
I have some tasks that has to be executed within a time span defined by a
start date and an end date.
I want to see a superior (Level 1) task, where start date and end date
defines the earliest start date and the latest end date of all subordinate
(Level 2) tasks. If I accidentally go beyond the bound dates given by the
superior task the tasks should be marked specially or a warning should pop
up.
Have anyone "out there" an idea how I solve this problem?
In the very end I am going to write a VBA-macro, that create both the
superior task and the subordinate tasks.
Then it is only manual work to push and pull the subordinate tasks to fit in
the superior time span.
Using: MS Project prof 2003
Ebbe
Hi
I have some tasks that has to be executed within a time span defined by a
start date and an end date.
I want to see a superior (Level 1) task, where start date and end date
defines the earliest start date and the latest end date of all subordinate
(Level 2) tasks. If I accidentally go beyond the bound dates given by the
superior task the tasks should be marked specially or a warning should pop
up.
Have anyone "out there" an idea how I solve this problem?
In the very end I am going to write a VBA-macro, that create both the
superior task and the subordinate tasks.
Then it is only manual work to push and pull the subordinate tasks to fit in
the superior time span.
Using: MS Project prof 2003
Ebbe