sync issues with 'Tasks' view.

T

TM

I have noticed that when I update task information using
MS Professional 2002, the updates (such as % completes) do
not make it to the my 'Tasks' view.

(Note: the project web view does get updated/sync'ed up,
it is the 'Tasks' view thats the problem.

Thanks!
 
G

Gary Chefetz [MVP]

TM:

Open your project plan from the server
Select the tasks that you updated in Project
Select Collaborate > Publish > Republish Assignments
In the dialog box, make sure that select items is selected at the top
At the bottom, select the checkbox to overwrite actual work in Project Web
Access
Click OK
Voila! All synched up.

--
Gary Chefetz [MVP]
http://www.msprojectexperts.com

*** Remember to look for line breaks in links posted to the news group, use
cut and paste for these.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top