P
Phanidhar
Hi,
I'm using MSP 2003. In my project we work for 9 hrs per day and to reflect
it, I've changed the "hours per day" option in Tools->Options-> Calendar.
I've also set the project calender accordingly using Project->Change Working
Time option.
Now, the MSP shows the correction duration but the actual distribution of
effort is still 8 hrs per day only. For e.g. if I've the work as 27 hrs, the
duration field would display as 3 days, but the actual work allocation would
span for 4 days (8 + 8 +8+3). So the difference between the start date and
end date is actually not three days but 4 days.
How can I set the MSP to allocate 9 hrs per day actually?
Thanks
Phanidhar
I'm using MSP 2003. In my project we work for 9 hrs per day and to reflect
it, I've changed the "hours per day" option in Tools->Options-> Calendar.
I've also set the project calender accordingly using Project->Change Working
Time option.
Now, the MSP shows the correction duration but the actual distribution of
effort is still 8 hrs per day only. For e.g. if I've the work as 27 hrs, the
duration field would display as 3 days, but the actual work allocation would
span for 4 days (8 + 8 +8+3). So the difference between the start date and
end date is actually not three days but 4 days.
How can I set the MSP to allocate 9 hrs per day actually?
Thanks
Phanidhar