T
Tony
I was wondering if there is a way to control the duration of a task by
assigning resources to it?
For example, if I have a 40 hour task and assign one resource to it
(resource is set to 8hr work day) the task would be completed in 5 working
days. If I assign two resources, the task would be complete in 2.5 days.
Is this possible?
Thank you,
Tony
assigning resources to it?
For example, if I have a 40 hour task and assign one resource to it
(resource is set to 8hr work day) the task would be completed in 5 working
days. If I assign two resources, the task would be complete in 2.5 days.
Is this possible?
Thank you,
Tony