C
CeeTee
I'm currently using MS Project 2000 - it may be upgraded to Project 200
in the near future.
I've created a project with a milestone at the project start, an
another milestone at the project finish.
I want to add a task, which is Supervision, which will have an effor
of 2 hours per week, and I want this task to start when the projec
starts, and finish when the project finishes, and add 2 hours per wee
for that duration.
So if the project goes out by (say) two weeks, then an extra two week
of supervision, at 2 hours per week, gets added to the project, and t
the cost.
I've tried a number of things, but I seem to finish up with either
couple of days of task duration at the end of the project, or I have t
manually add in the task duration for the effort to calculate against
neither of which is what I want.
Can this be done?
Thanks for any comments.
Regards
in the near future.
I've created a project with a milestone at the project start, an
another milestone at the project finish.
I want to add a task, which is Supervision, which will have an effor
of 2 hours per week, and I want this task to start when the projec
starts, and finish when the project finishes, and add 2 hours per wee
for that duration.
So if the project goes out by (say) two weeks, then an extra two week
of supervision, at 2 hours per week, gets added to the project, and t
the cost.
I've tried a number of things, but I seem to finish up with either
couple of days of task duration at the end of the project, or I have t
manually add in the task duration for the effort to calculate against
neither of which is what I want.
Can this be done?
Thanks for any comments.
Regards