Task End Date in Non-Working Data

R

Raja

Hi,

I've a task, When the resources booked time on the task through the PWA the
end date of the task was changed. But now the end data falls on a non-working
day. how is this paossible. i also have the stadard calendar Enterprise
global set for that day as non-working day. Is there any other setting in
project server for enforcing the task to move the end-date before or after
the non-working day.
 
W

Wiley

Raja,

First check the calendar assigned to the Resource (look on the Resource
Sheet). This is the calendar used to schedule resource time. My guess is
that he/she si assigned to a different calendar by default which does nto
reflect the same no working day.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top