S
Sinister
I have a two software developers that want to hammer out a schedule for a
design project they are working on. We have gone through and identified 31
tasks. Each is Fixed work. We have assigned both of them on each task.
Developer 1 puts 75% on every task and Developer 2 puts 50% on every task.
The problem begins when we try to identify the dependencies. According to
them there are none. Their rational is that they go back and forth between
tasks all the time. So, they all start at the same time. Obviously this wont
due considering on the first day Developer 1 has to work 88 hours while
Developer 2 works 72.
So, how do you schedule tasks that a resources bounces around on on any
given day?
Thank you in advance.
design project they are working on. We have gone through and identified 31
tasks. Each is Fixed work. We have assigned both of them on each task.
Developer 1 puts 75% on every task and Developer 2 puts 50% on every task.
The problem begins when we try to identify the dependencies. According to
them there are none. Their rational is that they go back and forth between
tasks all the time. So, they all start at the same time. Obviously this wont
due considering on the first day Developer 1 has to work 88 hours while
Developer 2 works 72.
So, how do you schedule tasks that a resources bounces around on on any
given day?
Thank you in advance.