Task linking with offset

F

frank

Instead of linking tasks finish to start I would like to
put in an offset.

Example: Start of task B is linked to the Finish of Task
A minus 7 days.

Or the Start of TASK B is linked to the Start of Task A
plus 3 days.

I only seem to be able to Link Start to Finsh or Finish to
start.

Any Advice?
 
G

Gérard Ducouret

Hello Frank
If you want to introduce a lead time of 7 days if the predécessor is on the
10 th row : enter 10FS-7d in the Predecressor column.
If you want to introduce a lag time of 3 days, you'll enter the 10FS+3d
link.

Hope this helps,

Gérard Ducouret
 
M

Mike Glen

Hi Frank,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series of Microsoft Project lessons in
the TechTrax ezine, particularly Lesson 3 at this site:
http://tinyurl.com/2xbhc

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 