F
frank
Instead of linking tasks finish to start I would like to
put in an offset.
Example: Start of task B is linked to the Finish of Task
A minus 7 days.
Or the Start of TASK B is linked to the Start of Task A
plus 3 days.
I only seem to be able to Link Start to Finsh or Finish to
start.
Any Advice?
put in an offset.
Example: Start of task B is linked to the Finish of Task
A minus 7 days.
Or the Start of TASK B is linked to the Start of Task A
plus 3 days.
I only seem to be able to Link Start to Finsh or Finish to
start.
Any Advice?