R
Raja
Hi,
I've a particular task that has a duration of 3d. The task is of type fixed
duration. The task has two resources assigned to it. also the task is a
predecessor to another task. Now the resources booked time for two days and
both the resources made the remaining work as zero after booking time for two
days. But in the project plan the precentage complete of the task is shown as
only 67 % but actually the remaining work is zero. How could i solve this
problem ? is there any calculation setting i have to do?
I've a particular task that has a duration of 3d. The task is of type fixed
duration. The task has two resources assigned to it. also the task is a
predecessor to another task. Now the resources booked time for two days and
both the resources made the remaining work as zero after booking time for two
days. But in the project plan the precentage complete of the task is shown as
only 67 % but actually the remaining work is zero. How could i solve this
problem ? is there any calculation setting i have to do?