I have the need to view Task fields in the Resource view.
Is there a way from the Resource Usage view to also view
Task fields that correspond to a specific task? Can you
create a single view that incorporates task and resource
fields?
Thanks in advance,
Cheryl
 
S

Sean

Cheryl:

Split the pane and select multiple views. That's your
best solution.

Hope this helps!
 