Task RTF notes

T

T J Mathew

Hi ,

how can i update the task notes( task_rtf_notes) field in msp_tasks. i have
tasks that have been allocated resources , and i need to insert task notes
for the tasks. i tried to do a binary update of the task_rtf_notes field and
also set the task_has_notes field to 1 and also the
msp_projects.proj_ext_edited field to 1 , but i could not see the task notes
on opening the project in msproject professional . I could read the same
binary task notes using VB direclty from the database , and it gave me the
correct data.

I use project 2002 Server and professional

does anybody have a code of the above that works ?

Thanks ,

T J Mathew
 