Krzysztof
Working with Project Server I've noticed that My Tasks includes tasks which
are already closed/completed and tasks of finished projects. I tried to
change it bu task settings but althouht you can define number of days for
current tasks - they are desplayed in a wrong way.
"Current tasks are those tasks which:
have started but not yet finished,
or have been rejected and not yet resubmitted
or are not older than or further in the future more than [7] days."
Generally all tasks are desplayed in My Tasks - how to correct it?
are already closed/completed and tasks of finished projects. I tried to
change it bu task settings but althouht you can define number of days for
current tasks - they are desplayed in a wrong way.
"Current tasks are those tasks which:
have started but not yet finished,
or have been rejected and not yet resubmitted
or are not older than or further in the future more than [7] days."
Generally all tasks are desplayed in My Tasks - how to correct it?