Task Start Date

M

Merryl

I have entered a task start date and set the constraint to Start no earlier
than however it instantly changes the date to 1 month later. How do I get my
original date?
 
J

Jan De Messemaeker

Hi Merryl,

There must be a reason.
- Project start date later?
- Dependencies from an other task?
- Task Calendar?
Resource availablility?
Automatic resource leveling?

After all, you say no earlier than, and that's what id does, doesn't it?
 